1.
Download Open Project from http://sourceforge.net/projects/openproj/
2.
Install and run the Open Project software.
Create
a New Project
1.
Create a new project.
• Project
Name: FnameLname Project–where Fname is your first name and Lname
is your last
name
• Manager:
ProfessorMiller
• Start
Date: 7/1/13
2.
Copy Range A2:F21 from the Data File.
3.
From within Open Project, select the first cell under the Name
column, and paste the clipboard
contents.
NOTE:The
resource names didn’t copy over. Also, the 2 hour Verify task now
shows as a .25
day
task. This is telling, a day in Open Project is an 8 hour period.
4.
Copy Range F3:F21 from the Data File. (Unnecessary
step)
5.
From within Open Project, select View from the Menu and then select
Resources.
6.
Under the Name column, add the following names: BA, DEV, TEST, INFRA,
TRAIN.
7.
From within Open Project, select View from the Menu and then select
Gantt.
8.
Refer to your Data File, under the Resource Name column; assign
resources to each task
separating
multiple resources on the same task by semicolon.
NOTE:If
you want to delete a Resource, DO NOT use the Delete key or you will
Delete the
entire
task. Use the Backspace key instead.
Categorize
the Work and Create Predecessors
1.Now
let’s categorize the work like it is in the Excel spreadsheet. From
within Open Project, select
rows
2 through 8 and while selected, click the Indent (Greater than sign)
on the menu. Do the
same
for rows10–12,
14–16, and 18–19respectively.
2.Now
let’s create predecessors, by placing the predecessor row number in
the appropriate
predecessor
column cell, for the following:
• Review
Requirementsfollows Document Requirements
• Design
Software follows Review Requirements
• Develop
Software follows Design Software
• Test
Software, Fix Bugs, and Validate Requirements follow Develop Software
• Design
Infrastructure follows Review Requirements
• OrderSoftware
and Hardware follows Design Infrastructure
• Install
Software and Hardware follows Order Software and Hardware by 5 days
(the lead time
for
Delivery). 1
Hint:Row
Number + 5 days
• Design
Training Materials follows Review Requirements
• Capture
Screen Shots follows Fix Bugs
•Deliver
Training follows Capture Screen Shots
• Deliver
Product to Production follows Software Development Work,
Infrastructure Build out
Work,
and End User Training by 1 day
• Verify
Delivery follows Deliver Product to Production
Confirm
1.
Questions
•From
the Gantt view, confirm the start and finish day/times for each of
the 4 major blocks of
work
for this project
• From
the Network view, confirm the critical path activities for this
project, in order.
Hint:Critical
path items are outlined in Red
• From
the Task Usage View, confirm work hours for each of the 4 major
blocks of work for this
project
• From
the Resourc