Student Details | |||||||||
| Student Number | 1 | 0 | 4 | 8 | 0 | 2 | 9 | 1 | |
| Student Number | 1 | 0 | 4 | 3 | 1 | 5 | 6 | 0 | |
| Student Number | 1 | 0 | 4 | 6 | 7 | 7 | 2 | 9 | |
| Student Number | 1 | 0 | 3 | 4 | 3 | 4 | 0 | 6 | |
| Family Name | DEMA | Given Name | Tshering | ||||||
| Family Name | TASHI | Sonam | |||||||
| Family Name | TSHEWANG | Jigme | |||||||
| Family Name | WANGCHUK | Druptho |
- The information on this coversheet will be included in Turnitin’s similarity analysis; however, your lecturers are aware of this and will disregard it.
Unit Details | |||
Unit Code | MAN5402 | Unit Title | Project Scheduling and Control |
Name of Lecturer | Mr. Richard Hughes | Due Date | 19/05/2019 |
Topic of Assignment | Project Proposal | Group or Tutorial (if applicable) | Group |
Course | Master of Project Management | Campus | Joondalup |
| I certify that the attached assignment is my own work and that any material drawn from other sources has been acknowledged. This work has not previously been submitted for assessment in any other unit or course. Copyright in assignments remains my property. I grant permission to the University to make copies of assignments for assessment, review and/or record keeping purposes. I note that the University reserves the right to check my assignment for plagiarism. Should the reproduction of all or part of an assignment be required by the University for any purpose other than those mentioned above, appropriate authorization will be sought from me on the relevant form. |
Manual Submission | ||||
| If handing in an assignment in a paper or other physical form, sign here to indicate that you have read this form, filled it in completely and that you certify as above. | ||||
Signature | Date | OfficeUseOnly | ||
Electronic Submission | ||||
OR,if submitting this paper electronically as per instructions for the unit, place an ‘X’ in the box below to indicate that you have read this form and filled it in completely and that you certify as above. Please include this page with your submission. Any responses to this submission will be sent to your ECU email address. | ||||
Agreement | select check box | Date | ||
For procedures and penalties on late assignments please refer to the University Admission, Enrolment and Academic Progress Rules – rule 24, and the ECU Course and Unit Delivery and Assessment Policy |
| The ECU English Language Proficiency Measure (Feb 2014) | ||||
| Levels ofproficiency Aspectsof writing (Indicate with an X main area(s) needing improvement) | Lowproficiency Incorrect or inappropriate aspects of writing obscure meaning in many places. Significant editing needed to clarify the meaning, along with extensive proofreading to correct technical errors. | Developing proficiency Incorrect or inappropriate aspects of writing obscure meaning in some places. Some editing needed to clarify the meaning, along with extensive proofreading to correct technical errors. | Moderateproficiency Aspects of writing are mostly accurate. Mistakes rarely affect clarity of meaning. Minor editing needed to clarify the meaning, along with careful proofreading to correct technical errors. | Highproficiency Aspects of writing are appropriate and optimally constructed, allowing clarity of meaning. Meaning is clear and needs only a light proofread to correct technical errors. |
| Sentencestructure 1. sentence completeness 2. sentence length 3. phrase/clause order 4. use of conjunctions 5. word order 6. punctuation | ||||
| Worduse 7. word choice 8. word form 9. word omission/redundancy 10. verb tense/agreement 11. spelling 12. apostrophes | ||||
| SentenceStructure 1. Sentence completeness: sentence includes subject, verb a complete thought. 2. Sentence length: length is appropriate to context or disciple 3. Phrase/clause order: parts of the sentence (phrases and clauses) are ordered logically. 4. Use of conjunctions: linking words are used correctly to show the relationship between ideas. 5. Word order: words are ordered correctly in a sentence. 6. Punctuation: the correct use of full stops, commas, semicolons, colons and capitals. | WordUse 7. Word choice: words are correct and appropriate for the context. 8. Word form: correct part of speech is used, e.g., [to] affect / [the] effect. 9. Word omission/redundancy: words should not be missing or be unnecessarily repetitive. 10. Verb tense/agreement: correct use of verbs that indicate time and correct word forms that agree grammatically with other words in the sentence. 11. Spelling: correct spelling is used. 12. Apostrophes: indicate ownership or contraction. |
Table of Contents
1 Introduction 1
2 Defining the Project 1
2.1 Project vision 1
2.2 Scope Statement 1
2.2.1 Objective 1
2.2.2 Deliverables 2
2.2.3 Milestones 2
2.2.4 Technical Requirement 2
3 Project Work Breakdown Structure (WBS) 2
3.1 Initial Survey 2
3.1.1 Market Analysis 2
3.1.2 Location 2
3.1.3 Name of the Company and its Slogan 2
3.1.4 Legal Requirement 2
3.2 Company Registration 3
3.2.1 Company Business Nature 3
3.2.2 Company Registration Type 3
3.2.3 ABN Number Application 3
3.2.4 Company Name 3
3.2.5 Website Address Domain Name 4
3.2.6 Purchasing the Website Domain Name 4
3.3 Budget Planning 4
3.3.1 Defining Budget Source 4
3.3.2 Return on Investment Analyses 5
3.4 Cost Estimation 5
3.4.1 Fitness and Office Equipment Cost 5
3.4.2 Hiring Cost 6
3.4.3 Staff Salary 6
3.5 Technical Documentation 6
3.5.1 Feature of the Website 6
3.5.2 Content of the Website 7
3.5.3 Feature of the Mobile Application 7
3.5.4 Feature needed from the Backend Server 7
3.5.5 Design of the Website 7
3.5.6 Design and Layout of the Mobile Application 7
3.6 Development of the Website and Mobile Application 8
3.7 Development of Fitness Centre Outlet (Building hiring) 8
3.8 Renovation of the Building (Interior Designing) 10
3.9 Procurement of Fitness Equipment and other Items 10
3.10 Recruiting Staff 11
3.10.1 Advertise the job vacancy 11
3.10.2 Shortlist the resume 11
3.10.3 Call shortlisted candidate for the interview or formal discussion 11
3.10.4 Recruit the fitness centre helping staff 11
3.10.5 Recruit full-time fitness coaches 11
3.11 Marketing the Business 12
3.11.1 Marketing plan 12
3.11.2 Digital marketing 12
3.11.3 Print media marketing 13
3.12 Fitness Centre Launch 13
4 Project Assumptions 14
5 Project Time and Cost Estimation (Top-Down, Ratio and Apportion Method) 14
5.1 Types of cost 14
5.1.1 Direct cost 15
5.1.2 Indirect cost 15
6 Project Scheduling 16
6.1 Developing project network 16
6.2 Project scheduling problem 18
6.3 Problems with crashing method 19
6.4 Resource scheduling 22
6.5 Resolution 22
7 Project Monitoring and Control 22
8 Project Summary 24
9 References 27
1Introduction
This document is about the setup of new business called Personal Fitness and Training Centre “FitStar Fitness” in Wembley suburb of Western Australia. The main objective of this document focuses on defining the project, its scope, deliverables, milestone, networking, time and cost estimation, monitoring, control including constraints, addressing problems and recommendations with respect to this fitness centre setup. The report also centres in scheduling numerous activities involved in setting up this business and registering it with the government. In depth, analysis of business has been carried out in order to make sure that correct type of business can be set up so that products or services of the newly set up business can reach to the maximum number of the audience. As a project team, the mandatory requirements of business domain analysis and the proper market study has to be done to make the strategic decision and taking the decision in favour of business entity. This document will also discuss the legal and federal laws required for setting up of the fitness centre and elaborate on the prerequisite of the project to ensure that business can be started on time as per the planned schedule. The project is initially planned to be started, executed, implemented and commissioned at a total cost of AUD 50, 724.70 (AUD fifty thousand seven hundred twenty-four and seventy cents) with a forecasted duration of 126 days.
This document has been framed based on the guidelines in Project Management Book of Knowledge (PMBOK).
2Defining the Project
2.1Project vision
The vision of “FitStar Fitness” aims to instil the value of health and fitness in every people’s lives enhancing better quality of life through various facilities, products and fitness philosophy.
2.2Scope Statement
In this phase, the project team decided what to do in the personal training domain and how to provide the service. Therefore, after a long discussion within the team members, it was finalised to provide a full-fledged personal training service for the people in Western Australia. Therefore, personal training and fitness coaching will be given effectively by considering the following list of scopes.
2.2.1Objective
The main objective of the project proposal is setting up and opening of personal health and fitness trainer and coaching, and fitness activities outlet in Western Australia in order to meet Australian fitness goals, which is expected to start from 1st July 2019 and complete by 3rd November 2019.
2.2.2Deliverables
- Initial analysis of business domain
- Detail WBS elements of the project
- Creation of project network from the WBS
- Project scheduling
2.2.3Milestones
Table 2.2.3: Project milestone
| Task Description | Duration forecast |
| Initial Survey | 1st July to 14th July 2019 |
| Company Registration | 15th July to 21st July 2019 |
| Budget Planning | 15th July to 21st July 2019 |
| Cost and Estimation | 22nd July to 4th August 2019 |
| Technical Documentation | 5th August to 18th August 2019 |
| Mobile Application and Website Development | 19th August to 30th August 2019 |
| Building Hiring | 19th August to 23rd August 2019 |
| Renovation and Interior Design | 31st August to 15th September 2019 |
| Procurement | 16th September to 5th October 2019 |
| Staff Recruitment | 6th October to 22nd October 2019 |
| Marketing | 23rd October to 31st October 2019 |
| Fitness Launch | 1st November to 3rd November 2019 |
2.2.4Technical Requirement
- Resources like consultants
- Experts for website and mobile application development
- Capital
- Other fitness facilities
3Project Work Breakdown Structure (WBS)
The Project work breakdown structure (WBS) can be defined as “hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables” (SmartSheet, 2019). WBS represents organised list of deliverables or outcome-oriented project work activities which are represented with a help of graphical display. Its main objective is to organise and subdivide the complete work scope of a project (Project Management, 2017). Further, work breakdown structure is the identification of the various sub-task against each of the task so that it can be ensured that none of the tasks is missed. Likewise, the project team has thoroughly discussed and has come up with the following work break down structures:
Figure 3.1: Work Break Down Structure Link
Each of the work activity in WBS is explained as below:
3.1Initial Survey
3.1.1Market Analysis
Market survey was conducted to the focused group for knowing the viability of starting Personal Trainer Business. It was found that about 75% of the people in the locality of the proposed Personal Trainer business supports the upcoming of the Personal Trainer in the area as they prefer working out is a way of staying healthy, reducing weight and getting good looking body. Not only that 25% are willing to get a membership and join the fitness immediately.
Apart from this, fitness owners who are already successful in this field were also consulted by the team to have better understanding on what made them take up this business and have it still running successfully.
3.1.2Location
After carrying out market research based upon the anticipated customers, Wembley suburb of Perth, Western Australia was seen to be suitable location for setting up of Personal Trainer business owing to its easy accessibility by foot, car and public transport.
3.1.3Name of the Company and its Slogan
Having discussed on the business name for couple of days, we decided to go by the name “FitStar Fitness” which was also available in ASIC Connect website. With the slogan of the company, “Fitness for ALL”, the “FitStar Fitness” will be a destination for attracting people of all generations who wants to stay fit and strong.
3.1.4Legal Requirement
To start the “FitStar Fitness”, there are various legal requirements to complete and follow up which includes:
- Business Permits and Licenses.
- State and Local Taxes.
- Federal Taxes.
- Business Laws and Regulations.
- State licensing guidelines for building zoning and consult legal experts for requirement of any other permits.
- Permits from local authority.
3.2Company Registration
3.2.1Company Business Nature
As the team have done the thorough analysis of the available business option, after lots of discussion and as per our interest, the personal trainer business shall be started which aimed to provide the personal trainer to those people who are looking for the personalized fitness coach.
3.2.2Company Registration Type
Considering number of factors into account prior to finalizing type of company to be registered, it was finally decided that the Personal Trainer business would be registered as a partnership firm among the four (4) people. The team will be running the company and shall be liable for everything. “FitStar Fitness” would also provide in-house training at the centre as well as on-call services for the clients who feel comfortable working out at home.
3.2.3ABN Number Application
Australian Business Number is a unique number which identifies one’s entity to the government and other companies. This number are also used for the tax purposes. Registering and applying for ABN is free and can be applied online or in person. During the process of ABN registration, the personal and business information need to be provided. The detailed business activities and the purpose of the application should be justified. “Your ABN is a unique number that allows you to identify your business to government and other businesses” (Business.gov.au., 2018).
3.2.4Company Name
Finalizing and choosing a company name would be a tough task. Certain guidelines should be followed with reference to a country’s law. It is also essential to know how to choose names for new companies. The naming is a crucial decision as the company name gives the first impression of what our business is dealing with. We decided to name our company as “FitStar Fitness” and therefore, checked in ASIC Connect website.
3.2.5Website Address Domain Name
The domain name takes 75% of the company name, easing the people trying to reach to take company’s services. Our domain name is our website adress online for the customers with our unique identity and brand. While creating the website name, it is always advisable to include our business name and the names that can be easily remembered. In order to create web addresses, it is required to register the company with an Australian Business Number. The domain name can be registered by going to .au Domain Administration website links. We finally accepted our website address as fitstarfitness.com.au.
3.2.6Purchasing the Website Domain Name
For purchasing the website domain name, there is need to select good domain registrar followed by domain availability check. This availability check can be done using an online checker tool. The domain name can be searched and chosen from the best available options. Domain registration has to be done and verfication can be completed by purchasing online.
3.3Budget Planning
Budget Planning includes the formation of fixed objectives, the recording of authentic performance outcomes and performance evaluation in relation to established objectives (Gavrilova, 2019). Budget management systems are worldwide and have been viewed as a vital instrument when it comes to financial planning. The role of budget planning in this project is to offer a projection on expenditures and revenues and this is realized by putting up a framework on how a firm is likely to operate fiscally talking of a number of approaches, plans, and events.
According to Gavrilova (2019), a budget refers to the statement that businesses and auditors use for calculating the financial data of an organization over a specific period and it depends on how a business plans to achieve its goals and objectives. It is a guide to businesses to enable them to spend as planned and as per allocation of funds. If a new fitness (Gym) owner decides to use the budget, it will enable them to track the expenditures of the business, identify any unnecessary expenses and eliminate them, identify operations that require more funds and project the business’ profit. Failure to use a budget makes financial and business management a hard task.
3.3.1Defining Budget Source
Siahaan (2018) stipulates that a good budget provides a financial road map. It will enable the business to identify ways of developing and growing from one level to another while establishing the resources that are required to ensure that growth and development are affected. Additionally, the budgeting process would also be a powerful tool to enable the top management to run the business effectively to realize profits. It also helps in bolstering the revenue of the business. This is because it would enable the manager to have concrete numbers that could enable the business to secure more revenue from sources such as grants. It would also create better ‘top-line’ revenue that would promote the ability of the fitness center to enhance coverage of its mission. Additionally, it would ensure the availability of a steady cash flow that the business can use in securing loans for expansion and improvement of projects (Jara-Bertin, Pinto-Gutierrez, & Pombo, 2018). In line with this, the team felt that reliable budget source is very vital for successful execution and completion of the project, and accordingly agreed to avail finance from Common Wealth Bank of Australia.
3.3.2Return on Investment Analyses
Budgeting includes arriving at enduring budgeting choices for business operations. Return on Investment Analyses is both a control tool and decision-making in budget planning. It is important to perform return on investment analyses before making any investment decision and for choosing the best alternatives to set up the fitness center. Expenditure levels are calculated for different costs, depending on any fluctuations in the actual revenue. Fixed bills such as mortgages would be easy to predict from the fixed budget. However, variable expenses are entirely unpredictable. As such, the budget depends on activity levels. The actual revenues are input into the flexible budget after the closure of an accounting period, and it generates a budget depending on the inputs.
3.4Cost Estimation
“Forecasting project cost at completion is of great importance to project management success” (Narbaev, Marco, 2014). There is a need to review Cost-Volume analysis to better understand the operating cost, total cost, the unit variable cost, product fixed cost and the volume of production for the fitness center. Gaining a clearer insight of these factors will help the team to better understand the volume and activity of the centre as well as variable cost, selling price, all fixed costs and the mixture of sales. In addition, this analysis will show break-even points, the gross contribution to the profit, coverage factor, safety interval, and index. Therefore, the project team has come out with the total cost estimation prior to executing the project.
3.4.1Fitness and Office Equipment Cost
Cost estimation in fitness and office equipment cost refers to estimating the cost of equipment to be employed in the business and its operation. Fitness and office equipment for fitness business includes specially made rubber sold by the commercial gym equipment shops sold at AUD 2 per square meter. Benches are very basic equipment used in weight training and those to be purchased include flat, incline, decline, and preacher benches.
3.4.2Hiring Cost
Trainers for a fitness roughly go at AUD 40 to AUD 90 hourly in the U.S. Some of the factors that influence the hiring cost includes number and length of the sessions, type of session i.e. personal or group training, and location of the business. A standard gym in urban areas has an average of 22 members on a monthly subscription and about 18 members on daily membership. So, the bigger the population that is likely to convert, the bigger the population that is already exercising, the more of the mid-income health conscious kind, the better for the business and the higher the cost of hiring.
Once fitness centre is ready, the fitness coaches, office boys and front desk person who can help the people coming to our fitness centre shall be hired. We will also hire a team of 2-3 people who can handle the entire request coming from the website and mobile for any kind of inquiry or the request for the fitness coach. Therefore, this online support team will coordinate those tasks.
3.4.3Staff Salary
As a result of occupation variations, staff salaries diverge among the employees depending on what they undertake. Every occupation has a cost that is figured by combining indirect and direct costs of every activity or sector that is employed to carry out the duty. They want to make sure that the product and the individual job is marketable enough and will bring in enough income.
Table 3.4.3: Staff and Salary Detail
| Sl.No. | Staff position | Qty | Annual Salary (AUD) |
| 1 | Manager | 1 | 50,000 |
| 2 | Office assistant | 1 | 25,000 |
| 3 | Fitness coaches | 3 | 45,000 |
| 4 | Cleaner | 1 | 10,000 |
3.5Technical Documentation
3.5.1Feature of the Website
We decided that we would develop a unique features in our website that would attract our customers at their first glance into the website. On the website, we have focused more on facilities for the fitness and the professionals providing the trainings to our clients. We have considered a small fitness club caterring both inhouse and outdoor fitness facilities in the website.
3.5.2Content of the Website
Website content of this business will contain all the information regarding the fitness activity and services provided by the centre. The opening and closing timing of the sessions, variety of courses and their related fees. The content would also have the facility of call-to-action message button. It would also contain the photos, biographies and contact numbers of the personal trainers. Colorful images of nutritional diets and the testimonials provided by previous clients. The web would also contain the inspirational transformed body photos of people and equipment to attract clients. Above all, the website will have our company logo.
3.5.3Feature of the Mobile Application
A user friendly mobile application will be developed which can be easily accessible both by clients and employees. The features would involve attendance tracking for employees, certification tracking for the clients, online payment system, scheduling appointments and exercise library system to browse available equipment etc. These include the normal standard features like calender, classes, courses, communication and reportings. The app shall also incorporate the fitness plan and assessments along with nutrition program. The app should be available on iOS and Android free of cost. In addition to the mobile App, also set up a toll-free number for easy communication.
3.5.4Feature needed from the Backend Server
The server shall have enough storage to accommodate all information of App users as well as the web details. This will store all mail correspondences, images, texts, call records and financial transactions. The backend server would also be backed up for redundancy and emergency in another server at completely different location.
3.5.5Design of the Website
The finalization of the website design would have collaborated parts of website content and features. The design will be simple, user friendly and easily availble in Apple and Google playstore.
3.5.6Design and Layout of the Mobile Application
The main component of the mobile application would have all design features discussed earlier and the layout would involve membership management, dashboards and report, automated billing and payroll and online sales portal. All features on both the applications will have syncronization to each other making it easier for the users. The main features in both website and mobile app shall remain the same for both employees and clients.
3.6Development of the Website and Mobile Application
Once the project scope has been finalized then the requirement analysis would be done regarding the market situation. Initially, developing the business website would be done, which will provide the complete detail about the business and company and its offered services. Therefore, any user looking for the personalized fitness service can visit the website and check the offered services. The users via the chat option on the webs or directly calling the toll-free can make contacts to the centre.
Following steps shall be followed for both website and mobile application procurement:
- Prepare the tender documents containing technical specifications, financial details, conditions of contract and other special conditions.
- Tender invitation through advertisement in media. This will take a few days for the vendors to finish preparing the bids.
- Submission of tenders and bids opening in presence of project executives and vendor themselves.
- Shortlisting the bidders based on our criteria such as price, quality, vendor performance and other terms and conditions as per the ternder norms.
- Bid evaluation for all the bids and calling short listed vendors for the meeting.
- Choosing best vendor for supplying the website and mobile application.
- Signing contract with the selected vendor. This will comprise of contract document preparation and holding a meeting for final sign off to initiate the website and mobile application development. Here we can also have negotiation and changes incorporation if necessary.
- Monitor the development process and take the proper status update from the vendor.
- Ask vendors to give status progress and check for rectification and give feedback.
- Testing and commissioning the website by the vendor and verifing
- Testing and commissioning the mobile aplication after launching the website at a later stage.
3.7Development of Fitness Centre Outlet (Building hiring)
As the initial launch of the service, one fitness outlet operation shall be required so that attraction to the fitness centre could be done. The various building or apartment owners would be contacted for the opening of the fitness outlet. The best location with proper connectivity and large customer concentration would be chosen for the centre. Further, decision would be made on single storeyed building that will in-house all the fitness equipment, furniture, IT equipment, restroom, offices and kitchen.
The fitness centre suite will typically consist of a reception, office, changing rooms & toilets (including accessible facilities), fitness gym, studio(s), first aid room, plant room, storage, staff facilities appropriate to size of the facility. Following additional facilities shall also be looked into:
- Cafe and bar
- Retail outlets or concessions
- Swimming, training or leisure pools
- Health spas, e.g. saunas, steam rooms and pools
- Health and beauty treatments, e.g. massage, relaxation, alternative therapies, hairdressing and manicure
- Creche
- Squash courts
- Tennis courts
- Physiotherapy/sports injury clinics
The following factors are essential, and shall be considered for fitness centre location:
- The building’s location and orientation should be perfect
- The outlet entrance to be attractive, clearly defined and welcoming.
- Site should be easily accessible to roads and public transport facilities such as buses and trains and should have enough spaces for vehicular circulation, parking provisions for cars, bicycles, motorcycles and staff parking.
- A traffic analysis may be required to ascertain impact on the site and surrounding infrastructure.
- Adequate provision for accessibility in respect of both parking and building access – consider site gradients and avoid stepped or ramped approaches.
3.8Renovation of the Building (Interior Designing)
An interior designer needs to be hired for creating a plan and detailed scope of work, that may take few days for interviewing various professionals according to the expectations of ours. The next step involves creating a plan and schematic designs which gives the rough layout on the plan and modifications to be made inside the building to match the deliverables of the “FitStar Fitness” which may take few more days to get approved. Once the plan has been finalized, contractors with the favourable quoted cost of estimation for the renovation works are selected to execute the plan. There are various works required to do while renovating. These includes creating partitions of the rooms, painting works, set up and fixing of various equipments, etc.
3.9Procurement of Fitness Equipment and other Items
Once our fitness centre outlet is completely furnished, we will start with the procurement of fitness equipment, office equipment, IT equipment and other miscellaneous items. The budget planning and cost estimation which is done in the earlier section will be used here to formulate tender document for this procurement.
The following processes will be followed to carry out the procurement.
- Prepare the tender documents containing list of fitness equipment, office & IT equipment and furniture with quantity, quality, brand and full description, other tender terms and conditions
- Tender invitation through advertisement in media. This will take a few days for the vendors to finish preparing the bids.
- Submission of tenders and bids opening in presence of project executives and vendor themselves.
- Shortlisting the bidders based on our criteria such as price, quality, vendor performance and other terms and conditions as per the tender norms.
- Bid evaluation and price comparison, negotiations for all the bids and calling short listed vendors for the meeting.
- Check if the estimated budget can cover the prices quoted by the vendor, otherwise look for other suppliers or additional budget or drill onto the negotiation.
- Choosing best vendor for supplying items and giving the notification for the vendor.
- Signing contract with the selected vendor. This will comprise of contract document preparation and holding a meeting for final sign off to initiate the equipment supply and delivery. Here we can also have negotiation and changes incorporation if necessary.
- Monitor the manufacturing or delivery progress and take the proper status update from the vendor.
- Ask vendors to give status progress and check for rectification and give feedback.
- Delivery, quality inspection and checking other selection criterian as per the contract.
- Testing and commissioning the equipment istallation and final payment release. Place additional order if need arise.
3.10Recruiting Staff
3.10.1Advertise the job vacancy
Once the company has been set up, the job advertisement shall be done over the social media, company website and any other local newspapers. The advertisement will have no discriminatory language on basis of race, colour, gender or sexual orientation. The advertisement will have experience and quality requirements for the job with application submission deadline.
3.10.2Shortlist the resume
The hired staff would have huge influence in attracting or retaining clients taking the fitness services, therefore, recruiting right trainer is essential. The candidate will be shortlisted based on previous experience, right candidate for the post and judging the ready to work capacity. These shortlisted candidates shall be called forward for interview.
3.10.3Call shortlisted candidate for the interview or formal discussion
The shortlisted candidate shall be called for further interview. The candidates shall also be asked to submit the medical certificates during the interview. Interview questions would all be related to the physical fitness training and body transformation workouts.
3.10.4Recruit the fitness centre helping staff
The administration and helping staff shall also be recruited for the centre. These staff would be responsible for providing customer service to members in the fitness center.
3.10.5Recruit full-time fitness coaches
Recuitment of fitness coaches would be one of the important process of the company. A coach should have good experience in the health promotion with required knowledge over the health appraisal methods and demonstrate well versed knowledge of principals of fitness. The required number of coaches shall be recruited in the company.
3.11Marketing the Business
3.11.1Marketing plan
The purpose of developing the marketing plan is to grow a business by setting marketing strategies to increase and maintain sales and a strong consumer base (Warren, 2017). Jump Start happens to be a recent business who plans on offering the first-choice brand of breakfast bars for our target audience. Once underway we will develop our brand awareness in the community and develop more jobs within the society. Warren (2017) states that the plan should involve free of cost for the basic features. While the presence of gyms which have existed for over a year are an indicator that the business has promise you should not be blind to the intensity of competition. If the competition is intense then it means the business will have to work more to capture a share of the market. And if the population of target consumers is not growing then it means you will be competing for a limited number of customers. If the business is going to set up in a location where there is intense competition, then there is need to have a strategy to win over customers. This could include facilities and trainers, strategically located and easily accessible premises or fast-growing consumer population.
3.11.2Digital marketing
According to Stair & Reynolds (2016), designing a Database System to Support a Self-Service Email Marketing System called Effect Mail. Effect Mail refers to a non-complicated and cheap web base self-service software solution that can be employed to new email marketing users. This system is going to address and implement features like setting up an Effect Mail Account which could be free account and also allows you to become paid members to have advanced features. Effect Mail provides multi-user account facility for premium customers and has a very attractive pricing strategy. It also provides email marketing packages, creating a subscriber list, setting up a campaign and tracking a campaign. This system should be implemented using T-SQL and any data should be stored in a Microsoft SQL server database.
3.11.3Print media marketing
According to Kohler & Gründer (2017), new media are also known as online media such as social media marketing involves the use of social media platforms or social networking sites such as Facebook to develop, convey, provide, and discuss contributions that have benefits to a firm’s stakeholders. Social media marketing is important to marketers because it is a cheap way to interact with their markets and engage these markets throughout the entire buying phase. On the other hand, traditional media marketing also known as established media marketing involves the use of traditional media channels such as television, radio, and print publications by marketers to advertise and sell their goods and services to the consumers having access to these established media channels (Kohler & Gründer, 2017).
3.12Fitness Centre Launch
Business launching is one event, which would give first impression to the people present and the readers how the business would run down the line. Therefore, launching of the fitness centre was considered as an important affair by the team. After successfully completing this project, the arrangement was made for the launch which was scheduled on November 3, 2019.
Inspection and Testing is the first move to ensure that all construction and assembly of the equipment are placed as per requirement. This would give space for modification wherever required prior to the launch date. The next step would be to contact and invite influencers who can help reach out the new business to the customers. This would also mean contacting the social sites and media for advertisements. This would be followed with exciting the members involved for selling out the services. Briefing the employees regarding the services and the event would help in promoting the business during and after the launch. Talking and educating people during the launch would highly benefit in upholding the business. Ensuring to contact renowned bloggers and use medium for advertisement like TV, radio and social media.
4Project Assumptions
Following assumptions were considered while carrying out the fitness centre project proposal:
Table 4.0: Project Assumptions
| Sl. No | Description | Assumption |
| 1 | Budget Source (Financing) | Commonwealth Bank, 217A Main St, Osborne Park, WA |
| 2 | Planned Project Cost | AUD 50,726.70 |
| 3 | Cost Estimation | Wise assumptions based on reliable online sources and dealers in the market |
| 4 | Time Estimation | Wise assumptions based on past executed projects |
| 4 | Crash cost slope (CCS) | Formula: CCS = (Crash Cost – Normal Cost) / (Normal Time – Crash Time) |
5Project Time and Cost Estimation (Top-Down, Ratio and Apportion Method)
The time and cost estimation for the project follows top-down approach, ratio and apportion method. Since the project is not unique and there are already a few similar businesses in the market, estimates for time and cost are purely based on those estimates. This way, it gives complete estimation with little effort and reasonable accuracy (Gray & Larson, 2018).
Suppose for activities such as initial survey, company registration, technical document, building hiring and renovation, calculations are purely based on the assumptions that each activity might take certain number of days (14 days for initial survey-two weeks-10 working days-8 hours per day) and cost per hour (AUD 25 per hour) making the activity cost to AUD 2000 in 14 days as shown in the table 5. Same approach has been followed for other similar activities in the project. However, for fitness equipment, website and mobile application procurement, the individual item cost estimation is considered. The per unit prices of items are sourced from Flex Fitness Equipment, Perth, WA. Further, for the miscellaneous cost, business launch and marketing cost, the estimation is apportioned as 10 to 25 % of the project total cost.
5.1Types of cost
Estimating cost for project involves collection and analysis of market data in terms of materials, labours and price which are readily available for use (Gray & Larson, 2018). For this project cost estimation, two types of cost namely direct cost, indirect cost which also includes general and administrative cost are involved.
5.1.1Direct cost
Constitute initial survey, company registration, budget planning, expenses for cost and estimation task, technical documentation, developing website and mobile apps, building renovation and procuring equipment, building hiring, staff recruitment, marketing and business launch. The total direct cost for this project is AUD 50,724.70.
5.1.2Indirect cost
For this project, cost associated with stationaries, working lunch, transportation, refreshment is considered as indirect cost in addition to general and administration cost such as miscellaneous expenses which cannot be associated with any activities in the WBS element.
Table 5: Cost Estimation Detail
6Project Scheduling
Project scheduling is important and forms an integral part of any projects at all the stages from the initiation till the completion of the project. Project scheduling will help to allocate an optimal resource to activities involved in the project. This business uses the critical path method (CPM) for scheduling the project of personal trainer.
6.1Developing project network
Networking in project is one of the essential tools for planning, scheduling and monitoring project progress and depicts the activities to be completed, sequence, showing its predecessors and successors, time duration for each activity and critical path which is the longest path through the network from start to finish. It is constructed from the data gathered from the WBS and is a graphic flow chart of the project work plan. It serves as the framework for the project information system that will be used by the project managers to make decisions concerning project time, cost, and performance (Larson, 2017). The complete network and the activity information table for the project is shown in table 6.1 & figure 6.1 respectively, which clearly depicts the activity identity, activity description, preceding activity, normal activity time and normal cost.
Table 6.1: Information about WBS Cost and Time
| Activity ID | Activity Description | Preceding Activity | Normal Activity Time (Days) | Normal Cost ($) |
| A | Initial Survey | None | 14 | 2000 |
| B | Company Registration | A | 7 | 1000 |
| C | Budget Planning | A | 7 | 3000 |
| D | Cost and Estimation | C | 14 | 3500 |
| E | Technical Documentation | B, D | 14 | 2500 |
| F | Website & Mobile Application Development | E | 12 | 12740 |
| G | Building Hiring | E | 5 | 1500 |
| H | Renovation (interior design) | F, G | 16 | 3000 |
| I | Procurement | H | 20 | 14485 |
| J | Staff Recruitment | I | 17 | 2000 |
| K | Marketing | J | 9 | 2500 |
| L | Launch of Fitness Centre | K | 3 | 2500 |
As shown in the table 6.1, the project will kick off by initial survey that will take 14 days and will be carried out by two people, the project manager and project engineer. On the 15th day, two activities such as company registration and budget planning will take place in parallel. These two activities will be completed after 7 days. Right after the budget planning phase, cost and time estimation work will start and complete after 14 days. It will be followed by technical documentation which will take around 14 days for completion. The team will then start with website & mobile application development along with building hiring works, which is estimated to compete within 12 days and 5 days respectively. Once the appropriate building has been acquired, its renovation on interior design and modification will be carried out. The time duration for complete renovation is predicted to be 16 days. For the fitness centre, the main items in focus are equipment and its accessories, which will be procured within 20 days and then followed by staff recruitment of 17 days. Marketing is the core task when it comes to venturing into any kind of business, so accordingly this task will be performed within 9 days. Finally, the project will close by launching the fitness centre, which will probably take around 3 days.
Figure 6.1: Project Network Diagram
After forming the complete network, longest path or the critical path through the task are computed and path denoted by red arrow in figure 6.1 for activity ID A-C-D-E-F-H-I-J-K-L are found as critical path in this project.
6.2Project scheduling problem
For the execution of the project, we experienced that the entire work had excessive optimistic plan, leaving us with large time buffers in each activity. In order to make the project realistic, we felt the need to reduce activity time and do proper scheduling of the work. Developing a practical project schedule had its challenges.
Along with the above problems experienced by the team, there are few other problems which are associated with Project scheduling:
- Resource-constrained project scheduling problem- certain activities gets delayed due to insufficient resources required at that time interval.
- Time/cost trade-off problem- The project cost is seen to increase due to cutting back certain activity durations by allocating more resources to them.
- Payment scheduling problem- this problem arises when the cash flows of the project is maximized by the Project managers by scheduling some of the activities.
6.3Problems with crashing method
Comparable to many other projects, several constraints were faced by the team during the scheduling of this project. The project team considered various strategies to shorten the duration of the work, primarily with adoption of crashing method. There were numerous activities, which could be crashed for faster completion of the work, however, these came with some obstructions to increased project costs.
Table 6.3: Information about Crash Cost and Time
| Activity ID | Activity Description | Preceding Activity | Normal Activity Time (Days) | Normal Cost ($) | Max. Crash Time | Crash Cost ($)Slope |
| A | Initial Survey | None | 14 | 2000 | 1 | 200 |
| B | Company Registration | A | 7 | 1000 | 1 | 100 |
| C | Budget Planning | A | 7 | 3000 | 1 | 300 |
| D | Cost and Estimation | C | 14 | 3500 | 1 | 350 |
| E | Technical Documentation | B, D | 14 | 2500 | 2 | 125 |
| F | Website & Mobile App Development | E | 12 | 12740 | 1 | 1200 |
| G | Building Hiring | E | 5 | 1500 | 1 | 150 |
| H | Renovation (interior design) | F, G | 16 | 3000 | 2 | 150 |
| I | Procurement | H | 20 | 14485 | 1 | 1000 |
| J | Staff Recruitment | I | 17 | 2000 | 1 | 200 |
| K | Marketing | J | 9 | 2500 | 1 | 250 |
| L | Launch of Fitness Centre | K | 3 | 2500 | 0 |
For instance, the affordable activity that can be crashed with less crash cost was internal design and renovation. However, crashing of this activity to its maximum allowable time would have incurred high cost to our project. We could not risk this increase due to our budget and resource constraint.
Similarly, the same crashing technique is applied to other activities and could reduce the project time duration by 10 days with an increase in project cost by AUD 3,900. Since, the increase in cost is not huge and can be easily adjusted within our budget provision, the project time duration has been now being reduced to 116 days.
Figure 6.3: Network Showing Crashing Process
6.4Resource scheduling
During the inception of the project, we encountered some problems with resource scheduling due to fund allocation with respective to individual activities. We assumed that our resources would be available to us when needed, but this assumption had problem during the actual scheduling. The estimation of the costs was based on the realistic data from online sources of similar executed projects. The even smoothing of the resources was done on the non-critical activities like hiring of building and technical documentations.
6.5Resolution
In order to prevent the problems associated with estimating the duration of the project and to makeit as a realistic one, we added time frame to each task and also added a contingency time separately for each individual activity in our schedule. This helped in making our plan more accurate one with correct activity period.
By devoting some resources, crashing approaches were carried out on few activities to decrease each normal activity time. Reducing the number of crashing times of certain activities helped minimize the extra expenses (indirect and overhead costs). This facilitated in meeting within the limited budget allocated to the activity and project at large, therefore, lowering the problem of increased overall project cost.
We had liberty over the project end date as the project had no deadline from customer. However, we stood by managing the project duration within 18 weeks. Our proactive communication among the project team and the weekly review meeting helped manage for timely implementation and completion of the work.
7Project Monitoring and Control
Monitoring and control process help in keeping track of the individual activities and project at large by comparing and identifying the deviation between planned deliverable and actual outcome (Larson, 2017). It also assists the project team about the time and financial progress of various activities under the project. Typically, methods such as Gantt charts, control charts, milestones are used in monitoring and communicating the project schedule status. For this project, Gantt chart is used for monitoring the project progress since it is the most favoured, used and understandable.
Figure 7: Gantt Chart
8Project Summary
The personal fitness trainer and coaching centre, the “FitStar Fitness” is unanimously chosen by the team in view to its popularity and health benefits that is being provided to the users. The main reason for choosing this project is that the members felt the entire components (scope, cost and time) of project management system can be captured and learned in depth. “FitStar Fitness” was initially planned to be executed within 126 days starting from 1st July with an estimated cost of AUD 50,724.70. After carrying out each and every processes of project management with scheduling and control in focus, the project would be completed by 24th October 2019 with the crashed period of 10 days. The project at a glance is tabulated below.
Table 8: Project Abstract
| Sl. No | Item Description | As Per Planning | After Scheduling/Execution (crashed details) |
| 1 | Project Duration | 126 days | 116 days |
| 2 | Project Start Date | 1st July, 2019 | 1st July, 2019 |
| 3 | Project End Date | 3rd November, 2019 | 24th October, 2019 |
| 4 | Project Cost | AUD 50,724.70 | AUD 54,624.70 |
| 5 | Budget source | Loan from financial institution | |
| 6 | Budget Plan | AUD 55,000.00 | |
| 7 | Critical Path | A – C – D – E – F – H – I – J – K – L |
One of most essential components of framing a project proposal in setting up of any business entity is the formation of work breakdown structure (WBS) element (Miller, 2009). It is crucial as it is the starting point from where determination of project deliverables confirmed and once resources and time allocations are completed making it measurable, independent with clearly defined limits (Markgraf, Bert., 2019). All these characteristics attribute to attaining clear benefits of using well-defined work breakdown structure for the project such as but not limited to help prevent activities slip through cracks, facilitating effective communication and corporation between and among project team and stakeholders, prevent changes, provides basis for estimating staff, cost and time and identifying risk at activity level (Gray & Larson, 2018). The fitness centre project has been deliberated in length and the team has constructed twelve sets of major works (WBS) ranging from initial survey, documentation, acquiring company registration and legal and other clearances, renovation, procurement and delivery, marketing and business launching. They are reflected to be delivered with numerous subtasks embedded within them and represented in chronological order at the best assumption of the project team.
As it is inevitable for a project to have a number of problems and difficulties, the team has made cumulative efforts in taking corrective measures and solutions wherever necessary. There are list of difficulties and problems that the project went through while coming up with aforementioned WBS elements. Notable difficulties such as deciding on level and detail of activities under each WBS element that is basically not knowing where to stop making the list of tasks; incorporating every team member’s perception and views about the activities needed to build up the WBS element; arranging and sequencing the WBS elements for scheduling, and delegating and assigning resources, time and cost. The project also struggled in framing technical parameters, assigning cost and time for activities. Consultants and experts are required for technical documentation, website and mobile application and also individual cost of each equipment is essential to come up with realistic estimation for procurement.
As a corrective measure, the framing of WBS elements are completed when the activities described in it are clearly detailed for the team to schedule, budget and delegate the work. In response to dealing with multiple views, estimating cost and time planning, the team has always made a point in ascertaining the task in reference to earlier similar projects and making wise assumptions keeping in mind the guidelines of top-down, ratio and apportion method of project time and cost estimation and then moving ahead without wasting much time. When it comes to ascertaining the cost of equipment, cost of website and mobile application development, the team has referred one of the prominent equipment dealers in Perth, WA (Flex Fitness equipment and Trojan Fitness). For website development, the team referred the prices according to Mendes & Emilia (2019) and mobile application development (Souza, Laudson & Gibeon, 2014). For allocating time to each WBS element, the team has deliberated thoroughly and drawn purely based on assumptions according to similar existing projects as guided by top-down method of estimation.
Project networking is one of the essential tools for planning, scheduling and monitoring project progress and serves as the framework for the project information system that will be used by the project managers to make decisions concerning project time, cost, and performance (Larson, 2017).
A modality for this project followed following trail:
- A project network has been developed for this business case utilizing the critical path method (CPM) technique which has been developed from the past similar projects.
- The critical path (A-C-D-E-F-H-I-J-K-L) has been worked out for this business case and is estimated to take a total of 126 days (18 weeks) to complete the project.
- Once the critical path has been worked out, the business case also shows the crashing of the activity time to complete the project before the estimated timeframe. It has been noticed that as the project duration has been crashed to 116 days from 126 days, there is an increase in the direct cost of the project to AUD 54624.70 from AUD 50724.70 but reducing the indirect cost that can be incurred to the project.
- During the realistic planning and scheduling of this project, a situation of resource constraint condition has been developed while crashing activity-H (renovation-interior design). Therefore, the activity-H could be crashed to only one time even though it has two crash times.
The overly optimistic work plan during the estimation of the project can give large buffer times between activities, which can cause prolonged project duration. In order to make the project realistic, the project team opted various strategies to reduce the duration of the project, thus, this demanded for proper project scheduling. Constructing practical scheduling had their challenges.
The project team had to keep in consideration the scope, time and cost during the project scheduling. This means that a proper management of time and cost, keeping in mind the overall scope, has to be done during the process of scheduling. The other critical constraints that can be faced by the project team would be scheduling time and resources. In order to reduce the project cost and the duration, the scheduling of each activity was considered. Thus, the adoption of crashing method was carried out on activities with minimum crashing costs. Cumulatively, these crashing added expenses onto the project cost (direct cost). The team had to selectively choose on the types of activities and the number of times to be crashed in order to meet with our limited budget. Few activities were selected for crashing and each time the impact on the overall budget were compared. The crashing of critical path activity is compared and the least affected cost on the project were chosen as solution to the time reduction. This helped the team to utilize the limited budget at its best for earliest project completion.
Scheduling the resources was another challenge that the team faced. Due to inadequate budget, gristly fund allocation had to be made to complete the work within the threshold. The current market prices and cost escalation made the budget segregation relatively challenging. However, resource levelling on the non-critical activities like hiring of building and technical documentation made this segregation under the budget limit.
In this project, monitoring and control will help in understanding about progress of project and assist to track an individual activity by comparing and identifying the deviation between planned deliverable and actual outcome in terms of efforts, cost and schedule within the project schedule. As this project is small and straight forward, Gantt chart is found suitable for monitoring and control as it has numerous advantages over other methods and is favoured by most being easily understandable especially for non-technical management team. However, it also has several flaws when it comes to actual project implementation. It illustrates only the time frame of each activity and the project as a whole but does not clearly keep track of the works. This simple monitoring system do not give the financial progress of the project. Hence, it is not favoured for large and complex projects and thus not suitable for reporting purposes to stakeholders and investors. The team in the context of large and complex projects would recommend for using other computer software-based monitoring and control tools such as Microsoft project, project labour and SAP Project system. Another strain with respect to smooth flow of various activities is due to lack of expertise and shortage of human resources that lead to the doubtful project completion on time. This meant that a proper work flow would not take place among the team and therefore, delaying the overall project. In order to overcome this issue, consulting and hiring experienced people with prior knowledge on such similar projects would be the best choice.
With the effective utilisation of knowledge and learning gained from project scheduling and control unit and by referring numerous books and articles relevant to the project, the team could successfully compete this project proposal. This document can be a wise reference for users intending to establish such fitness centre in Western Australia as every approach was done realistically.
9References
Ahuja, V., & Thiruvengadam, V. (2004). Project scheduling and monitoring: Current research
status. Construction Innovation, 4(1), 19-31
Garg, S., & Yadav, S. (2014). RESEARCH PAPER ON PROJECT PLANNING AND MANAGEMENT.
Silva de Souza, Laudson & Soares de Aquino Jr, Gibeon. (2014). Estimating the Effort of Mobile Application Development. Computer Science & Information Technology. 4. 45-63. 10.5121/csit.2014.4405.
SmartSheet. (2019). What is a work breakdown structure in project management?
Stair, R. M., & Reynolds, G. W. (2016). Fundamentals of information systems. Australia: Cengage Learning.
Upwork. (2019). Common Challenges That Many Startups Face.
Warren, T. C. (2017). Developing a Personal Marketing Plan. Bulls-Eye! The Ultimate How-To Marketing & Sales Guide for CPAs, 65-79. doi:10.1002/9781119448679.ch5
The post MAN5402 Project Scheduling and Control appeared first on My Assignment Online.