| Team Name | Virtucon 5 | ||
| Project Manager | Peter Deng | ||
| Other Team members | Scott Lyons | ||
| Nicholas Nancarrow | |||
| Yohan Lefort | |||
| Name of system | WOGAC | ||
| Draft Design – Detailed PMP | 18/03/2018 | ||
| Report number | 1 |
| Team Name | Virtucon 5 | ||
| Project Manager | Peter Deng | ||
| Other Team members | Scott Lyons | ||
| Nicholas Nancarrow | |||
| Yohan Lefort | |||
| Name of system | WOGAC | ||
| Draft Design – Detailed PMP | 18/03/2018 | ||
| Report number | 1 |
- Contents
1. Introduction 2
Purpose of the project management plan 2
2. Product Overview 2
Assumptions 3
Constraints 3
3. Scope management 3
Work Breakdown structure 5
Change Control Management 5
4. Schedule Time Management 6
5. Cost/ Budget management 7
6. Quality Management 8
Quality Objective: 8
Key Deliverables: 8
Quality Assurance: 9
Quality Control: 9
7. Human Resource Management 10
8. Communication Management 10
9. Risk Management 11
10. Issue Management 14
11. Procurement Management 16
12. References 17
- Introduction
The project is proposed for the Globex Corporation for extending the office in different location such as Albury, orange, and cloud. In this paper we are looking forward to develop a proposal for establishing corporate network in different location for the expansion of Globex Corporation. The network management is required for managing effective communication between various offices which are geographically apart. The organization performance will be improved by enhancing the network support for sharing the information securely among various units of the enterprise. The development of the Secured virtual private network for the organization would help in managing effective communication between site location of the enterprise with the deployment of mesh topology for the management of communication for sharing of information and resources required.
.
- Project Overview
Earlier On we have chosen the network design for Albury, Orange and cloud based branches as our main project, we aim to distribute network system across all the branches which we will be implementing the same structure as all the existing Globex office branches. But the difference is that we will apply modern facilities and technology that will make the new branch a trial to success, and if succeeded then that network lay out will then be rolled over and will become the new network structure for the existing business system.
And to quickly look back on our proposed project is a brief overview of our proposed lay out for Globex Corporation.
Globex Corporation was founded in 2013 and was merger of two larger regional businesses to form the Virtucon Corporation and now has three office locations in Riverina region of NSW, one Albury, and one in Orange and Cloud Infrastructure. The brief receives by Virtucon was to design network infrastructure for the Three offices, Due to project risk and constraints it been mutually agreed by the team that Orange, Albury and cloud offices are in scope for this project. A fast paced environment that we are now living in; where everything should be rapid and instant from choosing what to wear, where to eat or even a quick catch up with family and friends the greatest strategy is to put everyone in a parallel universe where technology, business and livelihood can integrate.
This Network system project has been exclusively design with the primary aim of creating a state of the art network layout and administration for the initial trial of Globex branch to be built in Albury, Oranges and the cloud system. The main requirements are state of the art servers and administration that will distribute connection across the shopping centre, though an existing system distribution from the other branches are being implemented, the project sponsor allowed us to modify and convert the network distribution of the soon to be built branch in NSW.
The Globex communication is looking forward for the deployment of communication though virtual private network, mesh topology, and HTTPS network connection between the various units of the enterprise which are undertaken for the expansion of the project. The enterprise requires the upgrading of the existing infrastructure according to the requirement of implementing VPN in the curriculum of the business operational plan.
- Purpose of the Project management plan
1.1.1.The current network structure of Globex Corporation is out of date and is in urgent need of an update which will allow for secure VPN, full mesh topology communications as well as HTTPS connection via an intranet.
The rising number of staff and clients requiring information related to Globex’s agricultural services has created a need for a secure and reliable network structure.
The WOGAC project aims to address the needs of Globex by designing and building a new network that is reliable, efficient, secure and easy to use.
- Business Objectives of the Project
To be considered successful, the proposed project must achieve the following goals for the client:
| BUSINESS GOAL | EVIDENCE OF GOAL ACHIEVED | |
| The project will provide fast communication and reliable connection to all the Globex Branches | Globex corporation is able to achieve solutions and support staff and client base in a timely fashion without network failure or errors and with all processes completed with to be agreed upon response times. | |
| WAN connectivity must meet the expected uptime goal of being available at least 99 percent of the time annually | Monitoring of network uptime with logs kept of uptime and any downtime. Measure for any period to show downtime is less than 1 percent | |
| All communications between branches must be encrypted and secure using industry best technology | Thorough testing of communications will be undertaken to ensure all communications are encrypted. Stakeholders will sign off on agreed protocols to be utilised. Use of the agreed protocols will be demonstrated at hand over. | |
| All outbound and inbound connections between sites must be secured with adequate firewall protection installed | Configuration of firewall will be documented and tested thoroughly with stress testing designed to break through the firewall. External testing of the firewall will be undertaken using industry standard tools. | |
| The system must provide for authenticated external connection by staff and authorised clients and customers | Inter-site secured VPN access will be implemented by project engineering team and subjected to functionality and penetration testing prior to client handover. | |
| 7. | VoIP communications capability must be available for offices as well as staff and clients in the field. This will be software based. | Full testing and verification of scoped VoIP solution will be undertaken prior to handover to Globex. |
| 8. | The capability to design a company intranet and web site must be provided that staff will be able to access internally and externally once design is complete. | An under construction website is accessible internally and externally at completion of the project. Training and documentation for the intranet and website are provided allowing Globex corporation staff to assume role of building and design. |
| 9. | The system must support Globex corporation staff accessing the network both internally and externally. | A list of local and remote systems will be collated and hard metrics gathered for expected requirements as part of the project. This will be discussed, agreed upon and signed off by stakeholders. Stress and user testing will be performed as part of the project to ensure all hard metrics are met. Acceptable results will be signed off by stakeholders. |
1.2.Assumptions
- IEEE standards should be followed for the deployment of virtual private network
- Procurement plan should be capable of adequate supply of resources and equipment (Expertise of the System analyst)
- Accurate costing of the resources for the budget preparation
- Effective deployment of mesh topology
- Balance between cost and resources used
- Helps in facilitating the working capabilities of the employees.
1.3.Constraints
- Completion of the project within the prescribed time: The project of deploying virtual private network should be completed within the scheduled time so as to improve the efficiency and effectiveness of the Globex Corporation.
- Completion of the project within the prescribed Budget: The distribution of resources and cost should be done within the approved budget of the project so as to complete the project without any complexities.
- Scope management
The expansion of the Globex Corporation to the Albury, Orange and cloud are facing problems in handling the events occurred at site location and inefficiency of managing information and resources among the different units of the enterprise. The proposal of deploying virtual private network with the support of Infrastructure as a service cloud model would requires the integration of the following activities. The following table shows the in-scope and out of scope activities with the project.
| In-Scope activities | Out-of-scope activities |
| Establishing communication with the deployment of virtual private network, mesh topology, and HTTPS network connection | Development of the maintenance program |
| Communication management between the expansion of the business units | Development of the operational program |
| Security mechanism used for the transmission of confidential information | |
| Increasing capability and productivity of the working employees | |
| Upgrading the infrastructure according to the requirement of implementing VPN in the curriculum of the enterprise | |
| Project should be completed with the approved budget and cost | |
| Implementation of VLAN for management network congestion and control | |
| Legal issues associated with the governmental agencies should be resolved | |
| Development of database for handling big data generated from the site locations | |
| Development of quality monitoring and auditing program | |
| Development of secured network | |
| Completion of the project within the expected timeline of the project |
1.4.Work Breakdown structure
1.5.
1.6.
1.7.Change Control Management
The change control management focuses on changing the working capability of the Globex Corporation with the deployment of virtual private network in the working curriculum of the enterprise. The inclusion of cloud services helps in developing effective communication between internal and external employees. The change management plan helps in identifying the risks associated with the project and review of action plan for taking effective step to improve the working structure of the firm.
- Schedule Time Management
- Cost/ Budget management
| Cost benefit analysis | ||||||
| Year 0 | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | |
| Net economic benefit | $114,000 | $114,000 | $114,000 | $114,000 | $114,000 | |
| One time cost | ($450,000) | $0 | $0 | $0 | $0 | $0 |
| Recurring cost | $10,000 | ($6,000) | ($6,000) | ($6,000) | ($6,000) | ($6,000) |
| Net cash flow | ($440,000) | $108,000 | $108,000 | $108,000 | $108,000 | $108,000 |
| Discount factors | ||||||
| Discount rate | ||||||
| Year Index | 0 | 1 | 2 | 3 | 4 | 5 |
| Discount factor | 1 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 |
| Discounted flows | ||||||
| Cost | ($450,000) | ($6,000) | ($6,000) | ($6,000) | ($6,000) | ($6,000) |
| Benefit | $0 | $114,000 | $114,000 | $114,000 | $114,000 | $114,000 |
| Net | ($450,000) | $108,000 | $108,000 | $108,000 | $108,000 | $108,000 |
| Cummulative | ($450,000) | ($342,000) | ($234,000) | ($126,000) | ($18,000) | $90,000 |
| Net present value | $90,000 | |||||
| NPV in fraction | 1.188 | |||||
| IRR | 7% | |||||
| Payback Analysis | ||||||
| Fraction Row | – | – | – | – | – | 2.57 |
| Partial years for negative cash flow | 2.57 | |||||
| Payback Period in Years | 2.57 |
- Quality Management
1.8.Quality Objective:
The objective of this project is to develop a project which is capable of maintaining efficient management of information and resources communication between the project sites of the Globex Corporation.
1.9.Key Deliverables:
- The quality management plan helps in analysing the problems associated with the deployment of VPN using cloud services
- management of process and procedures undertaken
- division of role and responsibilities among worker
- supply and demand of resources for the effective implementation of the project (PM4Dev, 2007).
- The accuracy of the information and project can be retrieved from the quality register.
- The proactive plan is developed for measuring the effectiveness of the proposed project in achieving the enhanced communication support between the various site locations of the Globex Corporation.
- The encryption and cryptographic standards should be used for preserving the confidentiality of the information which is shared between different units of the organization.
1.10.Quality Assurance:
The quality assurance of the project can be measured with the analysis of the standard and metrics, checklists of activities undertaken, peer review of the quality standards, and review of the effective communication for the proposed VPN network (Passenheim, 2015).
1.11.Quality Control:
The quality of the virtual private network can be improved by measuring the security mechanism used for making secured transmission of information and resources over the cloud (Mansfield Community, 2013). The control policies which are used for the proposed project are construction of the quality metrics for assessing the outcome with the requirement placed by the project owner, development of the checklist based on the requirement specification plan, auditing of the process and policies, and organization of the test plan.
Quality management plan for Globex Corporation
Quality control activities
Quality assurance activities
Quality development plan
Establishment of the Functional plan
Result
Pilot and Inspection plan
Decision making procedures
Quality strategic plan
Developing checklist for the Globex Corporation
Quality standards for the VPN
Test plan for assuring the quality of the project
Test Design
Operational structure
Flow chart construction
Use cases
Quality Improvement plan
Training and development program for enhancing Skills and Expertise of the stakeholders
- Human Resource Management
The following table shows the role and responsibilities of the Globex corporation team members associated with the project development plan:
| Team Members | Name | Responsibilities |
| Project Owner | The project Owner is responsible for placing their requirement for the management of effective communication between various units of the enterprise. The requirement specification plan clearly defines the need of virtual private network with the association of cloud services. | |
| Project Manager | Peter Deng | He is responsible for managing communication between Internal and external parties of the enterprise who are geographically apart He works on resolving quality issues and uncertainties associated with the project |
| Project Designer | Scott Lyons | He is responsible for developing the design for implementing VPN with Infrastructure as a service cloud platform (Collins, 2013) |
| Technical assistant | Yohan Lefort | He works on developing a quality assurance policies for taking proactive action plan for managing risks and issues associated with the project |
| Quality Manager | Nicholas Nancarrow | He is responsible for managing the quality control and checklist for getting expected output |
| System analyst | Peter Deng | He is responsible for managing the functional and non-functional requirement of the proposed project |
- Communication Management
| What | By Whom | How | When | To Whom |
| Information related to the contract and policies | External parties at different geographic location | Video Conference Information retrieving from the cloud | In a month | Project manager |
| Project Status Report | Project Manager | Emails | Daily | Project Owner |
| Minutes of meeting | Project Planner | Emails | Weekly | Project manager |
| Project Design Report | Project Designer | Meeting | Monthly | Project Owner and system analyst |
| Quality Report | Quality Manager | Meetings and Emails | Monthly | Project Sponsor |
| Risk Identified and mitigation report | Risk Manager | Emails | Weekly | Project sponsor |
| Procurement Report | Procurement Manager | Emails and Documentation | Weekly and as per requirement | Project Sponsor |
- Risk Management
| Risks | Likelihood | Risks Severity | Risks Likelihood | Risk Ranking | Evaluation | Risks Mitigation strategies | Review |
| Technical risks | Inefficiency in the project planning phase | 2 | 2 | 4 | Medium | Management of planning on the basis of requirement specification plan | Designer and planner |
| Project Design Risk | Inefficiency of the designing phase | 3 | 3 | 6 | High | The outcome of the design phase should be measured with the requirement specification plan | Designer and system analyst |
| Management of Required infrastructure | In the deployment of Mesh topology for connecting different site location of the Globex corporation | 3 | 4 | 7 | High | Quality standard plan for mesh topology to deploy VPN with the association of Infrastructure as a service cloud model | System analyst |
| Internal risks | Communication | 1 | 2 | 3 | Medium | Effective communication plan should be developed with the association of project stakeholders | Project Manager |
| Financial Risks | Wrong estimation of the cost in completing the project activities | 4 | 4 | 8 | High | Cost should be analysed for each and every scheduled resources and activities | Project Sponsor |
| Risks associated with time schedule | Analysis of critical activities | 4 | 4 | 8 | High | Analysis of the project activities with their scheduled time allocated | Project Planner |
| Risks associated with determining In-scope activities and out of activities | Privilege given to the out of scope activities | 4 | 3 | 7 | High | Determining activities on the basis of requirement specification plan for VPN | Project Manager and project Owner |
| Quality Risks | Inefficiency in the development of quality standard | 1 | 1 | 2 | Low | Checklist should be evaluated on the basis of expected outcome of the project | Quality manager |
| Communication risks | Inefficiency in the communication in the internal and external parties | 1 | 1 | 2 | Low | Information should be securely transmitted between various units of the Globex enterprise | Project Manager |
- Issue Management
| Types of Issues | Description | Managing Issues | Responsible person |
| Technical Issues | The supply and management of technical requirement for the implementation of the VPN | The Virtual Private network and cloud services helps in managing technical issues | Technical Assistant |
| Issues with creating design logic | Improper management of design logic for the placement of VPN to manage communication between various site location of the project (Miller and Yonek 2011) | Deployment of Mesh Topology for creating design logic gates | Project Designer |
| Security issues | Policies and procedures for the Implementation of the security in the VPN are inefficient for managing the secure transmission of information | The encryption and cryptographic standards should be used for preserving the confidentiality of the information which is shared between different units of the organization. | System analyst |
| Chaos and conflicts | Inadequacy in the working plan of the employees | Division of role and responsibilities with associate training and development program | Human Resource Manager |
| Financial Issues | Under budgeting of the project can result in the deficiency of managing supply and demand of the resources | Development of Budget and cash flow | Project Sponsor |
| Time Line Issues | Inefficiency in completing the critical activities of the project on time as scheduled in the time chart (Tsang, 2012) | Development of project schedule | Project Planner |
| Issues with the development of the project scope | Inefficiency in predicting in-scope and out of scope activities of the project | Development of project schedule with the proper division of in-scope and out-of-scope activities | Project manager |
| Quality issues | Incompetency in matching the output of the project as mentioned in the requirement specification plan for the secure transmission of information over various channels and site location (Belout, 2014) | Initialization of quality standards and metrics | Quality manager |
| Issues with the network Management | Issues with the deployment of mesh topology for the construction of virtual private network with different site location | Proper designing and implementation of project topology | Network administrator and system analyst |
- Procurement Management
The procurement management plan focuses on the purchasing of:
- Hardware support required for the implementation of virtual private network, mesh topology, and IAAS cloud model
- Software required for managing communication between external and internal parties
- Focuses on the services deployed by the vendor
- Implementation of consulting services
- Development of outsourcing requirement
- Initialization of training and development program for the employees (Lapin, 2014)
- Development of maintenance program
- Documentation of contract and agreement with the contractors and other stakeholders
- Initialization of the requirement specification plan for managing supply and demand of resources
- Division of work, resources, and equipment
- References
Belout, A. (2014). Effects of human resource management system on project effectiveness and success (1st ed.). Retrieved from https://www.sciencedirect.com/science/article/abs/pii/S0263786397000112
Collins, B. (2013). Design and implement a VPN for a medium office (1st ed.). Retrieved from http://eie.uonbi.ac.ke/sites/default/files/cae/engineering/eie/DESIGN%20AND%20IMPLEMENT%20A%20VPN%20%28VIRTUAL%20PRIVATE%20NETWORK%29%20FOR%20A%20MEDIUM%20OFFICE_0.pdf
Kaziliunas, A. (2012). Problems while implementing quality management system for a sustainable development of organization (1st ed.). Retrieved from http://www.su.lt/bylos/mokslo_leidiniai/ekonomika/2012_4_28/kaziliunas.pdf
Lapin, D. (2014). Proposing a cloud based operational model for IT infrastructure (1st ed.). Retrieved from https://www.theseus.fi/bitstream/handle/10024/85709/Denis_Lapin_16_12_2014.pdf?sequence=1&isAllowed=y
Mansfield Community. (2013). Introduction to project management (1st ed.). Retrieved from http://www.mansfield.vic.gov.au/Libraries/Community_Development/Intro_to_Project_Management_Manual.sflb.ashx
Miller, M., and Yonek, G. (2011). Implementing virtual private network for enabling lower cost (1st ed.). Retrieved from http://prod.sandia.gov/techlib/access-control.cgi/2001/012264.pdf
Passenheim, O. (2015). Project management(1st ed.). Retrieved from http://home.hit.no/~hansha/documents/theses/projectmanagement.pdf
PM4Dev. (2007). Project management organization structure (1st ed.). Retrieved from http://www.classtoolkit.org/sites/default/files/documents/PM4DEV_Project_Management_Structures.pdf
Rosu, S., Popescu, M., Dragoi, G., and Guica, I. (2012). The Virtual private network on IPSec VPN solution and management(1st ed.). Retrieved from http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.463.1057&rep=rep1&type=pdf
Seppala, R. (2013). Implementing a quality management system for an engineering and service company (1st ed.). Retrieved from https://www.theseus.fi/bitstream/handle/10024/91724/Seppala_Roope.pdf?sequence=1&isAllowed=y
Tsang, T. (2012). Procurement management system design and implementation (1st ed.). Retrieved from https://pdfs.semanticscholar.org/8354/7d658d66908570bc28cdd92f8a2bb3ad2ec5.pdf