Question 1: Provide a table outlining how you allocated the Resources (P1 to P8 and D1 to D7) across the Tasks. What is the minimum number of each resource necessary to ensure that the project is not delayed due to over allocation of resources?
Response: The table below indicates the resources assigned to every task for purposes of easing the completion process:
| Activity | Time taken in Weeks | Predecessors | Programmers | Designers | Resources Used in the activities | |
| 1 | 1 | 3.0 | 3.0 | P1,P2,and P4 | D1,D2, and D4 | |
| 2 | 2 | 1 | 1.0 | 1.0 | P1 | D1 |
| 3 | 1 | 1 | 1.0 | 0 | P3 | |
| 4 | 2 | 1 | 0 | 1.0 | D4 | |
| 5 | 2 | 1 | 2.0 | 1.0 | P2 and P4 | D2 |
| 6 | 3 | 2 | 1.0 | 1.0 | P1 | D1 |
| 7 | 7 | 3 and 6 | 0 | 2.0 | D1 and D4 | |
| 8 | 2 | 4 | 1.0 | 0 | P4 | |
| 9 | 4 | 5 | 1.0 | 0 | P2 | |
| 10 | 6 | 5 | 0 | 1.0 | D2 | |
| 11 | 1 | 7 and 8 | 2.0 | 0 | P1 and P4 | |
| 12 | 1 | 9 | 1.0 | 1.0 | P2 | D3 |
| 13 | 3 | 10 | 1.0 | 2.0 | P2 | D2 and D5 |
| 14 | 2 | 11 | 0 | 0 | P1 and P4 | |
| 15 | 3 | 12 | 0 | 1.0 | D3 | |
| 16 | 4 | 13 | 1.0 | 1.0 | P2 | D2 |
| 17 | 3 | 14 | 0 | 2.0 | D1 and D4 | |
| 18 | 5 | 16 | 1.0 | 0 | P2 | |
| 19 | 4 | 15 and 18 | 1.0 | 1.0 | P2 | D3 |
| 20 | 2 | 17 and 19 | 1.0 | 1.0 | P2 | D1 |
The image below is a screenshot of the MS project showing how the resources will be allocated.
Question 2: From the Network Diagram, note the critical path in red, and list the tasks in order on the critical path. Include a copy of the Network Diagram in your report.
Response: The critical path is presented as (Devaux, 2014):
The Network Diagram is as follows (Devaux, 2015):
Question 3: What is the finish date for the project?
Response: The expected completion date for the project is on Wednesday, October, 2nd , 2019.
Question 4: Use the Tracking Gantt Chart to investigate the non-critical activities. The Tracking Gantt groups them and shows the slack time as a blue line at the end of a dependent series. List each of these activities that have a slack time, and indicate the slack time. This is the Free Slack Time. We are not interested in the Total Slack which attributes downstream slack to upstream tasks and can be very deceptive.
Response: A screen shot of the MS project as developed and generated from the excel sheet is presented below for emphasis:
The table above indicates that some of the activities were not critical and there was a free slack time. The activities are captured in the following table:
| Activity | Slack Time (Free) in weeks |
| 2 | 0 |
| 3 | 4 |
| 4 | 0 |
| 6 | 0 |
| 7 | 0 |
| 8 | 8 |
| 9 | 0 |
| 11 | 0 |
| 12 | 0 |
| 14 | 0 |
| 15 | 10 |
| 17 | 6 |
Question 5: How much money is spent for each of the activities 1, 5, 8, 12 and 19?
Response: Activities 1, 5, 8, 12, and 19 incur costs of $24,000, $22,400, $6,400, $8,000, and $32,000 as simplified in the table below.
| Activity | Costs Incurred ($AUD) |
| 1 | 24,000 |
| 5 | 22,400 |
| 8 | 6,400 |
| 12 | 8,000 |
| 19 | 32,000 |
Question 6: What is the total project expenditure?
Response: The project has an expenditure of $419, 200.00
Question 7: a) What are the peak usages of each of P and D, and
Response: P has a peak usage of one hundred and sixty hours, whereas that of D is two hundred hours.
- b) In which weeks do these peaks occur? We want to know the maximum resources needed for each of P and D, and the exact weeks for each peak usage so that it can be correctly scheduled.
Response: The highest peak for P occurs in the second week (Week 2) while that of D takes place in two weeks. They are the 10th and the 11th weeks simultaneously.
References
Devaux, S., A. (2015). Total Project Control (2nd Edition): A Practitioner’s Guide to
Managing Projects as Investments. CRC Press
Devaux, S., A. (2014). Managing Projects as Investments: Earned Value to Business Value.
CRC Press.
The post Provide a table outlining how you allocated the Resources (P1 to P8 and D1 to D7) across the Tasks appeared first on My Assignment Online.