1
Project Plan
Picture Framer
2
Table of Contents
Executive Summary……………………………………………………………………………………………………………….. 3
Purpose………………………………………………………………………………………………………………………………… 3
Background…………………………………………………………………………………………………………………………… 3
Eliciting Requirements …………………………………………………………………………………………………………… 3
Client Requirements………………………………………………………………………………………………………………. 3
Scope……………………………………………………………………………………………………………………………………. 3
Assumptions …………………………………………………………………………………………………………………………. 3
Literature review…………………………………………………………………………………………………………………… 4
Materials and methods………………………………………………………………………………………………………….. 4
MS Project…………………………………………………………………………………………………………………. 4
Work Breakdown Structure (WBS) ……………………………………………………………………………….. 4
Project Network…………………………………………………………………………………………………………. 4
Schedule……………………………………………………………………………………………………………………. 4
Critical Path……………………………………………………………………………………………………………..4-5
Work breakdown structure…………………………………………………………………………………………………….. 5
Project Network ……………………………………………………………………………………………………………………. 5
Resources……………………………………………………………………………………………………………………………5-6
Schedule ………………………………………………………………………………………………………………………………. 6
Critical path ………………………………………………………………………………………………………………………….. 7
Tasks along the critical path…………………………………………………………………………………………. 7
Potential Issues …………………………………………………………………………………………………………………….. 7
Recommendations ………………………………………………………………………………………………………………… 7
Time …………………………………………………………………………………………………………………………. 7
Cost ………………………………………………………………………………………………………………………….. 8
Resources reallocated to owner- total cost……………………………………………………………………. 8
Reference List ……………………………………………………………………………………………………………………….. 9
Appendix A (WBS) ……………………………………………………………………………………………………………10-11
Appendix B (Project Network) ………………………………………………………………………………………………. 12
Appendix C (Resources) ……………………………………………………………………………………………………….. 13
Appendix D (Project Schedule) ………………………………………………………………………………………….14-16
Appendix E (Issue Response) ………………………………………………………………………………………………… 17
3
Executive Summary:
This project plan provides the client with measures in scheduling and control for the start up of
their picture framing business. It follows the steps required though three phases; project
management, initial start up and operational process. The project plan is developed based on
the client requirements, which include a budget of $52000 and to be completed within 6
months. The materials and methods such as a work breakdown structure (WBS), project
network, resource allocation and schedule are utilised in establishing the critical path.
The following are set of recommendations to ensure project success:
• Adding Resources – as the tasks that require completion along the critical path are
constrained by the resources allocated;
• Scheduling Overtime – this would increase the budget but ensure that the time restraint
is met; and
• Reallocating Resources – The owner could complete some task rather than relying on
other resources such as the business advisor and manager.
Purpose:
The purpose of this document is to demonstrate the scheduling recommendations and
considerations for a new framing business. It outlines the tasks to follow with time estimates
and resource allocation based on research conducted.
Background:
We received an enquiry by a client regarding the start-up of a new picture framing business. The
client had a set of business idea and expectations for the framing business. We have been
enlisted to adapt these requirements to a project plan, providing the client with means of
scheduling and control needed prior to production.
Eliciting Requirements:
We have gathered the following information from the clients through an initial client meeting to
ensure we understand their needs and defined the scope accurately as to minimise any
misconceptions about the requirements. We also then conducted our own research of past
projects and procured knowledge from industry professionals.
Client requirements:
The client is seeking guidance in the process of starting up a picture framing business. A budget
of $52000 with some flexibility is allocated to the project, as long as the project is completed
within 6 months so that they can enter the market prior to their competitor.
Scope:
The objective of this project is to assist the client with the process and requirements of setting
up a successful picture framing business. The project will be conducted over a 6month period
and will aim to provide the client with a scheduled work package. The project budget is $52000
with some flexibility allowed. First phase of deliverables is project management process,
second is the initial set up and the third is the preparation for operations.
Assumption:
• Budget overrun is accepted;
• All scheduling is accurate;
• Resources are available as required; and
• Project is time – constraint, cost – accept, and scope – enhance.
4
Literature review:
When starting a new business venture, it is crucial that adequate research is conducted on
similar projects, as well as other methodologies and their outcome. This provides a basis for
some common mistakes that can be avoided and possible successes that might be applicable to
the current project. According to McLaughlin (2009), it is vital that in order for a business to
succeed they would need to assign accountability, prioritise tasks and remain goal oriented.
This may sound like an obvious approach yet 50% of new businesses will fail within the first 5
years due to the absence of a business plan and proper feasibility assessment (Investopedia,
2009). The following project plan follows the steps outlined by Pinson and Jinnett (2005), to set
up a successful business. These methods agree with those highlighted on the New Business
webpage by the Australian Government (2019), therefor we have formed the project plan
accordingly.
Materials and methods:
Developing an accurate project plan relies on thorough research of the field in question, as well
as past projects. Considering our team’s limited experience in a business of this nature, utilising
many online sources and expert opinions was necessary to form our proposed businesses
structure, schedule and to identify the key milestones we would need to reach. These include:
MS Project
MS Project was utilized to form the initial WBS and from there the project network and
schedule. The project network identifies the forward pass and backwards pass; however, MS
Project calculates this and displays the critical path (Larson & Gray, 2018).
Work Breakdown Structure (WBS)
Initial research focussed on identifying deliverables, evaluating costs and assessing resources.
Once our research identified all the work elements required, we generated a WBS by breaking
down necessary milestones into its most simple deliverable components, called work packages.
This WBS is to act as an outline for the project, cataloguing every work package that would need
to be completed to deliver a successful project.
Project Network
The WBS gives the business its direction, the schedule gives it a timeline, but it’s still missing the
structure. A business requires an order of operations to determine which tasks in the WBS are
addressed first based on how long they would take to complete, and what other tasks are
dependent on them. The most accurate way of presenting this information is in the form of a
Project Network, and using estimates based on our research we determined the maximum and
minimum length of time each work package would take to deliver then prioritised them based
on which tasks proceeded others.
Schedule
While a WBS is essential for understanding what needs to be done, it doesn’t become a reality
until a schedule is applied. Our research into similar existing businesses gave us a timeline as to
how long it would take to have each work package completed and using this information, we
constructed a schedule that could predict the overall completion time of our business.
Critical Path
Ordering these tasks based on their duration is how a critical path is formed. Put simply, the
critical path is the shortest amount of time it will take to deliver a project and is comprised of
whichever activities will take the longest to complete. The idea of the critical path is to
determine when the most important tasks need to begin and end in order to avoid any delays on
5
the project, with less time-dependent tasks working around that critical path. In order to
achieve as accurate a critical path as possible, it’s important to take note of the earliest and the
latest possible time the task could be finished by, and to ensure each task’s dependencies are
clear.
Work breakdown structure
The initial WBS (refer to appendix A) was devised through a list of requirements based on
information we acquired through online sources and knowledge gathered from industry
professionals. Once all major deliverables were accounted for, we decomposed the tasks into
manageable work packages. Creating an early WBS is useful for determining resource allocation,
creating the schedule and determining predecessors, however more detailed information is
required before these extrapolations can be made.
Phases:
It was highlighted that there will be three main phases of the project plan, with subheadings
under each. Please refer to appendix A.
• Phase 1: Project Management
• Phase 2: Initial set up
• Phase 3: Prepare operations
The phases provide a set of milestones, as these will assist in keeping our stakeholders informed
on the progress of the project and assist in keeping the project on target to complete all the
work on time.
Project Network
The project network (refer to appendix B) is used for planning, scheduling and monitoring
project process. The project network is a visual display of the sequence, interrelationship and
dependencies of the activities that must be accomplished to the complete the project (Larson &
Gray, 2018) (PMBOK, 2017).
The project network was developed from the tasks we identified in the WBS. Work packages
from the WBS were used to build the activities needed to fulfil the deliverables in order to
determine what needs to be completed for a success picture framing business.
The project network shows the start and finish times for the activities along with the critical
path, when following the critical path, we can keep the project on track, but it still remains
important to ensure non-critical task also remain on track as to not cause unforeseen delays.
After identifying the activity early start times and late start times, the resources can be
scheduled and time-phases budgeted.
Resources
Types of resources (refer to appendix C) used in a project are people, monetary, equipment,
time, capital or any other required to complete a project. The main resource identified in
forming a framing business is people, time and monetary as the industry professionals are
expected to utilise their own equipment and materials.
‘People’ consisting of the following:
• Business Advisor;
• Accountant;
• Manager;
• Project Manager;
6
• Finance broker;
• Lawyer;
• IT Consultant;
• Owners; and
• Real Estate Agent.
We have identified the estimated time each task would require for completion from past
projects and aligned them with estimates by the industry professionals (people) identified
above. This provided us with a reliable estimated time required by each resource to complete
the tasks along the project network and the cost of completing these tasks in relation to the
resources.
‘Time’
The time available to complete the project is 6 months. The estimated time of completion is 6
months and 9 days.
It is recommended that the client consider “Adding Resources” as the tasks that require
completion along the critical path are constrained by the resources allocated. “Scheduling
Overtime” is another solution. It is sometimes considered easier than “Adding Resources” as it
requires less communication and planning and the current resources are already familiar with
the project.
‘Monetary’
Client budget is $52,000.
Estimated cost is $56,876.
As the project is not constrained by cost but is constrained by time, the client accepts a cost
overrun.
The resources that require highest number of hours for the completion of the start-up are the
manager, business advisor and project manager. Please see appendix C for a detailed table.
However, it is not limited
The cost of each resource can be found in appendix C, the business advisor demands the most
monetary resources and has the potential to cause an undesired cost to overrun if tasks are not
completed within the scheduled time.
Schedule
The schedule (refer to appendix D) is constructed from the deliverables identified from the WBS
and predecessors determined from the project network. The schedule provides a logical
sequence of start and finish dates and available resources that are required to start a framing
business (Larson & Gray, 2018) (PMBOK, 2017).
Within the WBS we identified three phases, these phases informed the Schedule. Firstly, the
project management phase, this phase provides a checklist for us to prioritise the order of the
work processes. The second phase, the initial set up consists of self-assessment in which the
vision of the framing business is defined, identify skills is required and it is at this stage that the
final decision to proceed will be decided. If determine it is feasible to proceed, the main business
decision will be made, adequate marketing research and planning will be conducted and then
we will proceed with the requirements of business registration, prepare the finances and
register the business. It was determined that time would need to be allocated to prepare
finances and protect the business (refer to Appendix D for more details).
The third phase in the process is to prepare for operations, this phase encompasses the
previous two phases which have provided the foundation for the processes that are required to
7
successfully start-up operations. This phase focuses on the set up prior to the opening of the
business and includes tasks such as; setting up a website, understanding marketing and
establishing customer service, providing physical facilities and employing and training staff. The
concluding phase was imperative to the success of the project. Once this stage is completed, the
business can operate successfully.
Critical Path
(Refer to appendix B)
Tasks along the critical path:
Potential Issues
This plan is predicated on the assumption that there will be no issues during the planning and
scheduling stage of the project, or that these problems will be negligible. In the event that
adverse scenarios occur our team needs multiple plans of action in order to respond swiftly and
avoid delaying the project. In Appendix E we have outlined the most likely shortcomings this
project could face and provided guidance on how to proceed (Larson & Gray, 2018).
Recommendations:
Time
As it has been determined the project will run slightly longer than 6 months. It is recommended
that the client consider “Adding Resources” as the tasks that require completion along the
critical path are constrained by the resources allocated.
“Scheduling Overtime” is another solution. This would increase the budget but ensure that the
time restraint is met. It is sometimes considered easier that “Adding Resources” as it requires
less communication and planning and the current person is already familiar with the project.
8
Cost
The project is currently expected to run over budget. It is evident in appendix c that the owners
as a resource are underutilised. We recommend that the owner complete some tasks, as this will
reduce the overall budget by $20,312.00, (as outlined in the table below) rather than relying on
other resources such as the business advisor and manager. This could include tasks from:
The second phase – initial start up:
• 2.2 Make business decision
o Choose business structure; and
o Consider trademark.
• 2.3 Plan for success
o Researching the market and competition; and
o Research industry.
• 2.4 Register the business
o Register the business name;
o Register the ABN;
o Register the company; and
o Register licenses & permits.
The third phase – Prepare operations:
• 3.4 Provide staffing
o Interview and test candidates;
o Hire staff; and
o Train staff.
Resources reallocated to owner – total cost
| Name | |
| Project Management | $5,024.00 |
| Initial set up | $19,560.00 |
| Prepare operations | $11,980.00 |
| Total | $36, 564.00 |
It is imperative to project success that the plan and recommendations are followed or the client
would risk a budget blowout and not meeting the 6 month deadline.
9
Reference List:
10
Appendix: A
Work Breakdown Structure (WBS)
11
| D W D |
D W D |
D W D |
D D |
| P & | W D W D W D |
||
| k u d d % P u % d % |
|||
| P u d % |
|||
| P v d g | Bu dy g |
D
D
D
W D
W D
D
W D
D
C
D
C
D
D
D
C
D
C
D
R R D D D
P
| W d % |
d |
R g u
d
%
R
D
D
R N
W D
D
R
D
D
R &
D
D
P
W d
d
%
O
W D
D
P &
W D
D
&
D
D
W D
D
P
D
D
R
D
W D
O
P
D
D
u
%
U
D
C
D D W D
P v d P y
| W d % |
d |
W D D
D
D
P
D
D
W D
W D
D
H
D
D
D v
W d
d
%
P g u
A u g
d
W d d
%
D
D
u
d
%
A & u
R
W D
W D
C
D
D
D
D
P g
d
%
| u | u W d |
W d d
Appendix B
Project Network 12
17
Appendix E
Issue Response
The post the client with measures in scheduling appeared first on My Assignment Online.