(10 pts): What referenced item in the subcontract was not attached to the contract documents?
(10 pts): What did the parties do to recognize or rectify the issue in question #1?
(5 pts each): Did the contract documents have a liquated damages clause? If so, how much was it?Did the contract documents have an incentive payment clause? If so, how much was it?
(10 pts): Did the court award the subcontractor delay damages under any specific written provision of the contract documents? Why or why not?
(10 pts): What was the subcontractor’s alternative (or second) theory for seeking damages?