Limited Offer Get 25% off — use code BESTW25
No AI No Plagiarism On-Time Delivery Free Revisions
Claim Now

UNIT 3: Developing the Project Plan

Learning Objectives
• Explain the key issues associated with project
management.
• Describe how to apply the Critical Path Method
(CPM).
• Explain how to make time/cost tradeoff
decisions in projects.
1–2
Understand the following terms:
1–3

  • Network * Activities critical path
  • Event *critical
    activities
  • Critical Path
    4
    Network Diagrams
    • Network diagrams are the preferred
    technique for showing activity sequencing.
    • A network diagram is a schematic display
    of the logical relationships among, or
    sequencing of, project activities.
    • Two main formats are the arrow and
    precedence diagramming methods.
    Network Diagrams
    Activity-on-Arrow (AOA) networks
    – also called Arrow Diagramming Method (ADM)
    – Uses an arrow to depict an activity
    – simpler for projects with many dependencies
    – emphasizes events; milestones can be easily flagged
    – sometimes requires dummy activities
    Activity-on-Node (AON) networks
    – also called Precedence Diagramming Method (PDM)
    – Uses a node to depict an activity
    – easier to draw for simple projects
    – emphasizes activities
    – no dummy activities
    6–6
    Constructing a Project Network
    • Terminology
    – Event: a point in time when an activity is started
    or completed. It does not consume time.
    – Activity: an element of the project that requires
    time.
    – Merge Activity: an activity that has two or more
    preceding activities on which it depends.
    – Parallel (Concurrent) Activities: Activities that can
    occur independently and, if desired,
    not at the same time.
    6–7
    Constructing a Project Network
    • Terminology
    – Path: any route along the network from start to finish
    – Critical path: the longest path through the activity
    network that allows for the completion of all projectrelated
    activities; the shortest expected time in which
    the entire project can be completed. Delays on the
    critical path will delay the completion of the entire
    project.
    (Assumes that minimum of A + B > minimum of C in
    length of times to complete activities.)
    3 4
    5
    2
    6
    A B
    C
    D
    Situations in network diagram AON
    2–8
    Situations in network diagram AOA
    A
    B
    C
    A must finish before either B or C can start
    A
    B
    C both A and B must finish before C can start
    D
    C
    B
    A
    both A and B must finish before either of C or D can
    start
    A
    C
    B
    D
    Dummy
    A must finish before B can start
    both A and C must finish before D can start
    2–9
    A Comparison of AON and AOA Network
    Conventions
    Activity on Activity Activity on
    Node (AON) Meaning Arrow (AOA)
    A comes before
    B, which comes
    before C
    (a) A B C
    A B C
    A and B must both
    be completed
    before C can start
    (b)
    A
    C
    B C
    A
    B
    B and C cannot
    begin until A is
    completed
    (c)
    B
    A
    C
    A
    B
    C
    A Comparison of AON and AOA Network
    Conventions
    Activity on Activity Activity on
    Node (AON) Meaning Arrow (AOA)
    C and D cannot
    begin until A
    and B have
    both been
    completed
    (d)
    A
    B
    C
    D B
    A C
    D
    C cannot begin
    until both A and B
    are completed; D
    cannot begin until
    B is completed. A
    dummy activity is
    introduced in AOA
    (e)
    A C
    B D
    Dummy activity
    A
    B
    C
    D
    A Comparison of AON and AOA Network
    Conventions
    Activity on Activity Activity on
    Node (AON) Meaning Arrow (AOA)
    B and C cannot
    begin until A is
    completed. D
    cannot begin
    until both B and
    C are completed.
    A dummy
    activity is again
    introduced in
    AOA.
    (f)
    A
    C
    B D A B
    C
    D
    Dummy
    activity
    darla/smbs/vit 13
    AOA Project Network for House
    A
    2 0
    C
    3
    E F
    1 1 2 4 6 7
    3
    5
    Lay
    foundation
    Design house
    and obtain
    financing
    Order and
    receive
    materials
    Dummy
    Finish
    work
    Select
    carpet
    Select
    paint
    Build
    house
    AON Project Network for House
    A3 B2
    D3
    C1
    E1
    F
    1
    G1
    Start
    Design house
    and obtain
    financing
    Order and receive
    materials Select paint
    Select carpet
    Lay foundations Build house
    Finish work
    2–13
    3
    B
    1
    D
    1
    1
    G
    Constructing a Project Network:
    Table 3-1 A Sample Set of Project Activities and
    Precedence’s Activities
    2–14
    Activity Predecessor
    a —
    b —
    c a
    d b
    e b
    f c, d
    g e
    Constructing a Project Network:
    Figure 3-1 Stage 1 of a Sample AON Network
    2–15
    Constructing a Project Network:
    Figure 3-2 Stage 2 of a Sample AON Network
    2–16
    Constructing a Project Network: Figure 3-3 A
    Completed Sample AON Network
    2–17
    Critical Path Method (CPM)
    Critical Path – path with the longest total duration
    This is the shortest time in which the project can
    be completed.
    Critical Activity – an activity on the critical path
    *If a critical activity is delayed, the entire
    project will be
    delayed. Close attention must be given to
    critical activities
    to prevent project delay. There may be
    more than one
    critical path.
    Critical Path Method (CPM)
    Practical approach to finding critical path:
  1. identify all possible paths from start to finish
  2. sum up durations for each path
  3. largest total indicates critical path
    (This approach is inefficient, but is instructive)

The post UNIT 3: Developing the Project Plan appeared first on My Assignment Online.

Plagiarism Free Assignment Help

Expert Help With This Assignment — On Your Terms

Native UK, USA & Australia writers Deadline from 3 hours 100% Plagiarism-Free — Turnitin included Unlimited free revisions Free to submit — compare quotes
Scroll to Top